Redding Elementary School serves a culturally, linguistically, and ethnically diverse group of students who come from all over San Francisco. To the Redding School community, social justice and equity mean providing the highest quality education possible to all students so that they may succeed in our society.

General Information

Project Details

Architect:

Marshall Lee Inc.

General Contractor: Zolman
Construction Manager: Vanir Construction Management, Inc.
Bid Amount (Hard Cost): $13,223,147
Change Order Amount: $1,935,451   (14.64% of bid amount)
Final Contract Amount: $15,158,598

Project Description

Scope of work including but not limited to:

  • Voluntary seismic upgrades
  • Site re-grading, accessible ramps, fence/gates and game re-striping
  • Doors, frames and finish hardware
  • Plaster and gypsum board wall finishes
  • Epoxy and sheet linoleum flooring
  • Interior and exterior painting
  • Plumbing fixtures and miscellaneous equipment
  • Ductwork and electric control valve control system
  • Exterior and interior light fixtures
  • Fire alarm and clock/public address systems
  • Hazardous material abatement

This page was last updated on June 15, 2023