Harvey Milk Elementary School
![harvey milk](/sites/default/files/styles/embed_large/public/2022-10/20221028_091539.jpg?itok=wVbrYvaV)
Site map
To empower student learning by teaching awareness, acceptance and non-violence, celebrating our diversity, achieving academic excellence, and fostering strong family-school-community connections. At Harvey Milk Civil Rights Academy (HMCRA), you will be encouraged to become an active participant in your child’s educational journey.
![harvey milk](/sites/default/files/styles/max_590/public/2022-10/20221028_092741.jpg?itok=NGEfO43q)
Renovated Library
![harvey milk](/sites/default/files/styles/max_590/public/2022-10/20221028_092614.jpg?itok=NswlNtc0)
Upgraded Main Hallway
![Harvey Milk Civil Rights Academy](/sites/default/files/styles/max_590/public/2022-10/87232452_10157955896104709_9021497737740288000_n.jpg?itok=qfWSgVm_)
New Exterior Stairs
![harvey milk](/sites/default/files/styles/max_590/public/2022-10/20221028_093357.jpg?itok=bX_2Hs39)
Remodeled Multipurpose Room
![harvey milk](/sites/default/files/styles/max_590/public/2022-10/20221028_091520.jpg?itok=iU5yQFPM)
Exterior Façade of New Building Addition
Project Dashboard
General Information
Project Details
Architect: |
Gould Evans |
General Contractor: | Zolman |
Construction Manager: | Vanir Construction Management, Inc. |
Bid Amount (Hard Cost): | $13,110,000 |
Change Order Amount: | $1,140,609 (8.70% of bid amount) |
Final Contract Amount: | $14,250,609 |
Project Description
Scope of work including but not limited to:
- Demolition of existing portable classroom
- Recoat and restripe existing playground
- Construction of new 2-story addition
- Modernization of existing school main building which includes multipurpose room and classrooms
- Structural retrofit and voluntary upgrade
- Mechanical, electrical, plumbing, IT and fire protection system upgrade