Project Dashboard Link to this section
Project Details
Link to this section
General Information
Architect: | K2A Architecture + Interiors |
General Contractor: | Bana Builders, Inc. |
Construction Manager: | Kitchell Construction, Inc. |
Bid Amount (Hard Cost): | $12,279,253 |
Change Order Amount: | $1,411,717 (11.5% of bid amount) |
Final Contract Amount: | $13,690,970 |
Project Description
The project is generally described as general school modernization and reconstruction including ADA access, Seismic Upgrades, and Fire/Life/Safety upgrades, including but not limited to:
- Installation of interim housing utilities, coordination of IH delivery and install, new asphalt landings at IH ramps and final connection of MEP at Interim Housing bungalows.
- Multiple phases of hazardous material abatement, demolition of interior finishes, demolition of mechanical, plumbing and electrical systems.
- Restroom upgrades, new framing, new doors and hardware, new windows, new finishes, new plumbing, new mechanical, new electrical, new fire alarm, new low voltage, clock/PA, and exterior paint.
- Miscellaneous site improvements.
This page was last updated on June 17, 2022